Construction update: November 2026.

Published November 22, 2026· The Arête Team· Vol. 5 of a monthly series

Volume five. We skipped an October post, so this one covers two months, and they were big ones. In September the walls were going up as bare wood framing. Now the buildings are wrapped in sheathing, the window and door openings are cut in, the roof framing is going on top, and inside, the heating and cooling ductwork is going in.

Closed in and going up.

The biggest change from the outside is the sheathing. The wood panels now cover the framing, so the buildings read as solid walls with rows of window openings instead of open frames. Up top, crews are setting the roof framing.

Construction photo from November 2026: the front of an Arête building, framed and covered in wood sheathing, with rows of window openings and open ground-floor bays
Photo · sheathing on the front · November 2026
152
Phase 1 homes
Apr 2027
First homes open
Jan 2027
Applications expected
~516
Total at full buildout
Construction photo from November 2026: the corner of an Arête building in late afternoon sun, wood framing and sheathing with the roof framing going on above
Photo · the roofline goes on · November 2026
Construction photo from November 2026: the long side of an Arête building, framed and sheathed, with a fenced work area in front
Photo · the long side of a building · November 2026
“Two months ago these were open frames. Now they look like buildings.”
Construction photo from November 2026: looking up the side of an Arête building at the sheathed walls, window openings and roof framing against a cloudy sky
Photo · looking up the side · November 2026

Inside the framing.

Inside, the work has moved on to what goes in the walls and ceilings. The heating and cooling ductwork is being hung through the floor framing, and the interior walls that divide each home into rooms are framed. Wiring and plumbing run through the same spaces before the walls are closed up.

Construction photo from November 2026: metal heating and cooling ductwork hung between the wood floor framing inside an Arête building
Photo · ductwork going in · November 2026
Construction photo from November 2026: inside an Arête home under construction, wood stud walls and ceiling framing with round ductwork overhead and daylight through a window opening
Photo · inside a home · November 2026

New on the site.

The final 3D floor plans for the flats are now on our Floor Plans page: the one-bedroom, the accessible one-bedroom and the two-bedroom, each with a larger view. The first and second floor plans of the clubhouse are in the Gallery. For a walk through what Phase 1 includes, read From the plans: the amenities of Phase 1.

What’s next.

Next up is roofing and windows, so the buildings can be closed in against the weather, with wiring and plumbing continuing inside. The first homes are scheduled to open in April 2027, and applications are expected to open in January 2027. We’ll be back next month with new photos from the site.

Why subscribe.

Each month a little more of Arête appears. The same list gets first word on pricing, floor plans and when applications open.

Inside Arête

Want a preview while you wait?

See the homes and the plan these photos are building toward.

— The Arête Team · Southwest Meridian · November 2026 · Next update: December 2026